Photo by Raul Ling
The Scottish Government has granted offshore consent for the Muir Mhòr floating wind farm, one of the first commercial-scale floating projects from the ScotWind leasing round. The decision, announced on 19 November, allows up to 67 turbines with a capacity of up to 1GW around 63km off the Aberdeenshire coast. The Scottish Fishermen’s Federation (SFF) has strongly criticised the decision.
A milestone for floating wind
“This is an important milestone for Scotland’s offshore wind ambitions, with Muir Mhor offering significant potential to strengthen energy security, drive down floating offshore wind costs and unlock investment and jobs,” Public Service Reform Secretary Ivan McKee said. He added that, alongside Scotland’s 11 operating offshore wind farms with 4.3GW of capacity, there is now more than 11GW of consented capacity.
The Scottish Government says the wind farm could generate enough electricity for over a million homes a year. Its consent carries conditions, including mitigation for potential impacts on commercial fisheries and environmental compensation for potential impacts on seabirds.
Developer Fred. Olsen Seawind became the sole owner earlier this year after buying Vattenfall’s 50% stake. Project director David Hinshelwood described the decision as “a massive moment for Muir Mhòr”. The project already holds onshore consent from Aberdeenshire Council and is targeting first power in the early 2030s.
Fishing industry objections
The SFF says ministers have approved the project on weak evidence that fishing can continue alongside it. “In a serious blow to the Scottish fishing industry, ministers have signed off a 200-square-kilometre floating wind farm on important fishing grounds off Peterhead, including part of the Buchan herring spawning grounds and a valuable haddock fishery,” chief executive Elspeth Macdonald said.
The developer’s mitigation strategy proposes an obstacle-free zone of about 13 square kilometres, around 6.5% of the array, to keep grounds open to haddock and herring trawlers. Its final extent is still to be set with fishing companies, Baird Maritime reports. The SFF points out that the developer’s worst-case assessment assumes key fleets will not return to fish outside that zone over the wind farm’s 35-year life.
“Even with that proposal, the developer’s own assessment assumes key fleets will be shut out of much of the site for at least 35 years,” Macdonald said. “Proper provision should be made for where skippers can still fish safely and profitably, where displaced boats can go and what that will mean for the boats already fishing those grounds.”
A wider test for ScotWind
The decision is an early test of how floating projects will share space with fishing as ScotWind moves from leasing to consent. The SFF has renewed its call for a moratorium on further offshore wind consents. In October, MSPs backed in principle, in a non-binding vote, protection or compensation for fishers who face losses as offshore wind expands into established grounds. Last week we reported on SSE’s Berwick Bank B supply deal and growing concern over the future of Scotland’s offshore wind pipeline.